ITCertKing is continuing to provide the candidates with IT certification exam-related reference materials for years. ITCertKing.com is the website that is validated by all the test-takers, which can provide all candidates with the best questions and answers. ITCertKing comprehensively ensures the interests of all candidates, which enjoys immense praise of the candidates. Moreover ITCertKing is the most trusted website on the current market.

Life is full of choices. Selection does not necessarily bring you happiness, but to give you absolute opportunity. Once missed selection can only regret. ITCertKing's PMI PMI-001 exam training materials are necessary to every IT person. With this materials, all of the problems about the PMI PMI-001 will be solved. ITCertKing's PMI PMI-001 exam training materials have wide coverage, and update speed. This is the most comprehensive training materials. With it, all the IT certifications need not fear, because you will pass the exam.

Exam Code: PMI-001
Exam Name: PMI (Project Management Professional)
One year free update, No help, Full refund!
Total Q&A: 600 Questions and Answers
Last Update: 2014-01-26

In order to meet the needs of each candidate, the team of IT experts in ITCertKing are using their experience and knowledge to improve the quality of exam training materials constantly. We can guarantee that you can pass the PMI PMI-001 exam the first time. If you buy the goods of ITCertKing, then you always be able to get newer and more accurate test information. The coverage of the products of ITCertKing is very broad. It can be provide convenient for a lot of candidates who participate in IT certification exam. Its accuracy rate is 100% and let you take the exam with peace of mind, and pass the exam easily.

More and more people choose PMI PMI-001 exam. Because of its popularity, you can use the ITCertKing PMI PMI-001 exam questions and answers to pass the exam. This will bring you great convenience and comfort. This is a practice test website. It is available on the Internet with the exam questions and answers, as we all know, ITCertKing is the professional website which provide PMI PMI-001 exam questions and answers.

ITCertKing is a website which can give much convenience and meet the needs and achieve dreams for many people participating IT certification exams. If you are still worrying about passing some IT certification exams, please choose ITCertKing to help you. ITCertKing can make you feel at ease, because we have a lot of IT certification exam related training materials with high quality, coverage of the outline and pertinence, too, which will bring you a lot of help. You won't regret to choose ITCertKing, it can help you build your dream career.

Those who want to prepare for the IT certification exam are helpless. But they have to do it. So they have restless state of mind. However, With ITCertKing PMI PMI-001 exam training materials, the kind of mentality will disappear. With ITCertKing's PMI PMI-001 exam training materials, you can be brimming with confidence, and do not need to worry the exam. Of course, you can also face the exam with ease. This is not only psychological help, but more importantly, it allows you to pass the exam and to help you get a better tomorrow.

PMI-001 Free Demo Download: http://www.itcertking.com/PMI-001_exam.html

NO.1 Taking the following table into account, where would corrective action be MOST
effective when you make use of Pareto's Rule?
Origin of Problem Percent of Problems
Design 60
Development 15
Prototype 10
Testing 10
Fabrication 5
A. Development
B. Prototype
C. Fabrication
D. Design
E. Testing
Answer: D

PMI study guide   PMI-001   PMI-001 certification   PMI-001 exam dumps   PMI-001 dumps

NO.2 Which of the following is NOT an indirect cost?
A. Insurance costs.
B. Payroll tax cost.
C. Subcontract costs.
D. Accounting support costs.
Answer: C

PMI exam   PMI-001   PMI-001   PMI-001   PMI-001 questions

NO.3 Which of the following requires an expenditure of the resources when working
within an arrow diagramming method?
A. Histograms.
B. Accounting support costs.
C. Pareto diagram.
D. Milestone events.
E. Path activities.
Answer: B

PMI certification training   PMI-001   PMI-001   PMI-001   PMI-001

NO.4 Which of the following represents the BEST process to accomplish resource
planning?
A. Identifying the required resources in the project charter
B. Identifying the available resources and allocate them to all activities in the current
phase of the project.
C. Identifying the required resources and allocate them to all project activities.
D. Identifying the resources that performed past similar projects, and allocate them to all
project activities
E. None of the above
Answer: C

PMI   PMI-001   PMI-001 test   PMI-001 test   PMI-001

NO.5 Which of the following represents the final task during project close-out?
A. Reassignment of team member.
B. Verification that contractual obligations were met.
C. Transferring the deliverables to the client.
D. Completion of performance/lessons-learned records.
Answer: C

PMI exam dumps   PMI-001   PMI-001

NO.6 The "Cost of quality" project management concept includes ____?
A. The costs involved when changes are made to the requirements
B. The costs of ensuring that requirements are conformed to.
C. The costs incurred when requirements are exceeded.
D. The costs involved with quality control requirements.
Answer: B

PMI   PMI-001   PMI-001   PMI-001 questions

NO.7 Which of the following is the distinguishing characteristic between the network
diagram and the Gantt chart?
A. Few resources
B. Key milestones
C. Critical dates
D. Critical dependencies
Answer: D

PMI   PMI-001 exam simulations   PMI-001   PMI-001

NO.8 Under which of the following circumstances would project management is the NOT
be the preferred management approach?
A. Cross functional tasks.
B. Unique operations.
C. Product manufacturing environment.
D. Time-constrained deliverables.
Answer: C

PMI   PMI-001   PMI-001 practice test   PMI-001

NO.9 Which of the following represents a consequence to the project in the event of a
resource being added to the project team during execution?
A. Shorter project completion schedule.
B. An indeterminable effect.
C. A requirement for a scope change.
D. An increase in project quality.
Answer: B

PMI   PMI-001   PMI-001 exam dumps   PMI-001

NO.10 What does a benefit-cost ratio of 3.22 indicate?
A. A profit of s3.22 per unit produced.
B. A payback of s3.22 for each dollar expended.
C. The percentage of resources assigned to other tasks on the critical path.
D. The gold plating result.
E. A profit of s3.22 for each dollar expended.
Answer: B

PMI certification   PMI-001 pdf   PMI-001   PMI-001 dumps   PMI-001

NO.11 Which of the following is illustrated by a resource histogram?
A. The expected requirements for critical path activities.
B. The expected resource usage by time period.
C. The resource assignments by work package.
D. The resource assignments by activities.
E. All of the above.
Answer: B

PMI   PMI-001 test answers   PMI-001   PMI-001 exam

NO.12 Which technique would you be using if you analyze which sequence of activities has
the least amount of flexibility when you need to predict project duration?
A. Critical path
B. Dependency diagramming
C. PERT
D. Gantt chart
E. Monte Carlo method
Answer: A

PMI   PMI-001 certification   PMI-001 pdf   PMI-001

NO.13 Which of the following are indicative of duration estimates?
A. How many hours a resource will work on an activity.
B. When an activity is expected to start.
C. How many work periods an activity is expected to last.
D. When an activity is expected to finish.
Answer: C

PMI exam   PMI-001 original questions   PMI-001 certification training   PMI-001 certification   PMI-001 exam simulations

NO.14 Which of the following describes Fast Tracking?
A. Circumventing loopholes.
B. Developing workarounds for previous problems.
C. Increased project risk.
D. Getting people to work longer hours in overtime.
E. Meeting schedule objectives by adding resources.
Answer: C

PMI   PMI-001   PMI-001   PMI-001   PMI-001   PMI-001

NO.15 What is the job title of the person who is primarily responsible for the quality of
deliverables?
A. The quality control inspector.
B. The quality controller.
C. The design engineer.
D. The project manager.
E. The quality manager.
Answer: D

PMI test   PMI-001   PMI-001 pdf   PMI-001

NO.16 Which of the following are included in cost control? (Choose all that apply.)
A. Informing stakeholders of changes.
B. Preparing cost estimates.
C. Recording appropriate changes to the cost baseline.
D. Monitoring cost performance.
Answer: A, C, D

PMI certification training   PMI-001 exam   PMI-001 exam   PMI-001

NO.17 Certain resources have been added to tasks on the critical path so as to reduce the
project duration. As a result the plan should then be reviewed for the:
A. Possible lag time on other paths.
B. Resource assigned to other tasks on the critical path.
C. The most time consuming task remaining in the plan.
D. Emergence of a new critical path.
Answer: D

PMI   PMI-001   PMI-001   PMI-001

NO.18 Where does comparing actual to baseline schedules, examining the statement of
work, understanding cost overruns, and assessing risk all occur?
A. Stakeholder meeting.
B. Resource leveling activity.
C. Project audit.
D. Contract negotiation.
Answer: C

PMI answers real questions   PMI-001 questions   PMI-001 questions   PMI-001

NO.19 Which of the following represents the pinnacle of Maslow's hierarchy of needs?
A. Survival.
B. Self-actualization.
C. Safety.
D. Esteem.
E. Physiological satisfaction.
Answer: B

PMI   PMI-001   PMI-001 pdf

NO.20 In which of the following circumstances is it BEST to make use of the project
management approach? (Choose all that apply.)
A. Cross functional tasks.
B. Unique operations.
C. Product manufacturing environment.
D. Time-constrained deliverables.
E. Production-line environment.
Answer: A, B, D

PMI test   PMI-001 exam simulations   PMI-001 test answers

NO.21 Which of the following statements depicts the key difference between contract
close-out and administrative closure?
A. Contract close-out formalizes project completion.
B. Contract close-out includes product verification.
C. Contract close-out includes updating records with final results.
D. Administrative closure includes procurement audits.
E. None of the above.
Answer: B

PMI certification training   PMI-001   PMI-001 exam simulations   PMI-001 certification training

NO.22 Which of the following should be done by the project manager upon completion of
the project?
A. Planning a turnover meeting.
B. Obtaining a sign-off from the customer.
C. Team celebration.
D. Project evaluation.
E. Performance evaluation of team members.
Answer: B

PMI certification   PMI-001 pdf   PMI-001   PMI-001 exam simulations   PMI-001

NO.23 What would be the cost performance index if BCWP =350, ACWP = 400, and BCWS = 325? Note:
Budgeted Cost of
Work Performed (BCWP), Actual Cost of Work Performed (ACWP) and Budget Cost of Work Schedule
(BCWS)
A. 0.813
B. 1.078
C. 1.143
D. 0.875
Answer: D

PMI test answers   PMI-001   PMI-001   PMI-001 questions

NO.24 Which of the following factors are NOT included in cost control?
A. Preparation of cost estimates.
B. Informing stakeholders of changes.
C. Monitoring cost performance.
D. Recording appropriate changes to the cost baseline.
Answer: A

PMI   PMI-001   PMI-001 exam   PMI-001   PMI-001   PMI-001 study guide

NO.25 Which of the following is NOT an essential regarding a project close-out?
A. Documenting formal acceptance of the product.
B. Documenting the final risk assessment.
C. Documenting the lessons learned.
D. Documenting the final project scope
E. None of the above.
Answer: B

PMI   PMI-001 test   PMI-001 exam dumps   PMI-001

NO.26 Which of the following statements BEST describes what project progress reports
are?
A. It is used to predict future status and progress.
B. The project sponsor makes the most use of it.
C. It is an important communications element.
D. It is needed on a weekly basis.
Answer: C

PMI test answers   PMI-001 test questions   PMI-001   PMI-001   PMI-001   PMI-001

NO.27 Which of the following is the MAIN reason for including incentive clauses in a
contract?
A. Reducing costs to the buyer.
B. Controlling contractor costs.
C. Aligning contractor and buyer goals.
D. Reducing production costs.
E. Reducing contractor risk.
Answer: C

PMI braindump   PMI-001 test questions   PMI-001 exam   PMI-001   PMI-001

NO.28 Consider the following situation: The customer was given a monthly report that
indicates zero schedule variance. One of the teams members are aware of at least
one milestone that has not been achieved. This missed milestone will result in an
overall delay in the project.
Which of the following items were not reported on adequately?
A. Critical path status
B. Risk analysis
C. Communication plan variance
D. Resource management plan
E. All of the above
Answer: A

PMI study guide   PMI-001   PMI-001 braindump

NO.29 Which of the following is NOT included in activity duration estimated?
A. Project team knowledge.
B. Commercial duration databases.
C. Time studies.
D. Information from previous experience.
E. None of the above.
Answer: C

PMI demo   PMI-001 answers real questions   PMI-001 test questions   PMI-001 pdf   PMI-001 demo

NO.30 When preparing the probability distribution of cost outcomes for a project, what is
the estimate with a 15% probability of being exceeded approximately one standard
deviation ___________?
A. Above the mean.
B. Below the mean.
C. Below the median.
D. Above the median.
Answer: A

PMI dumps   PMI-001 dumps   PMI-001 certification training

ITCertKing offer the latest C2040-442 exam material and high-quality 1Y0-300 pdf questions & answers. Our 1z0-457 VCE testing engine and 650-304 study guide can help you pass the real exam. High-quality MB7-700 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/PMI-001_exam.html

没有评论:

发表评论